Pilot Energy The Outlet: Unplugged

FERC's large-load orders

Written by Pilot Energy | Nov 17, 2026, 4:50:59 PM

On a napkin

Timeline of federal action on large-load grid interconnection, October 2025 to late 2026 Timeline with seven milestones. October 2025: DOE directs FERC to consider large-load interconnection rules. December 2025: FERC orders PJM to adopt co-location rules. January 2026: FERC approves SPP's High Impact Large Load process. April 2026: FERC commits to act by June. June 18, 2026, highlighted: FERC issues show cause orders to all six RTOs and ISOs. July 2026: 30-day resource adequacy reports due. August 17, 2026: 60-day tariff responses due, with several operators seeking to pause their dockets. An arrow points to regional tariff rules arriving from late 2026. Oct 2025 DOE directs FERC to act Jan 2026 SPP large-load process approved June 18, 2026 Show cause orders to all six RTOs/ISOs Aug 17, 2026 Tariff responses; pause requests Dec 2025 PJM ordered to set co-location rules Apr 2026 FERC commits to act by June Jul 2026 Resource adequacy reports due Next: regional tariff rules

Data as of September 30, 2026. Proceedings are active and moving; check the FERC dockets linked below for the latest filings.

The short version

On June 18, 2026, the Federal Energy Regulatory Commission issued six show cause orders, one to each grid operator under its jurisdiction: PJM, MISO, SPP, CAISO, ISO-NE, and NYISO. Each order preliminarily found that the operator's tariff lacks clear, fair rules for connecting very large electricity users, such as data centers and major manufacturing plants, and for loads co-located with their own generation. Each operator had to either defend its current rules or propose new ones.

This is the federal response to the biggest demand-side story in the power sector, data center load growth. It matters to every commercial buyer, not just data centers, because the rules being written now decide how fast new load connects, who pays for the grid upgrades it needs, and how much pressure it puts on capacity prices.

Key distinction: FERC has historically regulated how generators connect to the transmission grid. How customers connect has largely been a state and utility matter. These orders push FERC further into the load side than it has gone before, which is why states have pushed back.

How we got here

In October 2025, the Secretary of Energy used a rarely invoked authority to direct FERC to consider a rulemaking on large-load interconnection (Docket RM26-4). The proposal drew more than 3,500 pages of public comments. State utility regulators argued that FERC taking jurisdiction over load interconnection would intrude on state authority over retail service.

FERC had already been acting case by case. In December 2025, it directed PJM to adopt transparent tariff rules for load co-located with generation. In January 2026, it approved SPP's High Impact Large Load process for studying big loads alongside nearby generation. In April 2026, FERC committed to act on the broader docket by June. Rather than issue a single national rule, it chose six targeted orders under Section 206 of the Federal Power Act, a faster path that can be tailored to each region's market design.

What FERC is asking for

The orders ask each operator to address a common set of problems. They include:

  • Standardized study procedures so large-load requests are handled consistently and transparently. FERC suggested defining a large load as a new facility over 50 MW that takes transmission service above 69 kV.
  • Co-location rules that spell out rates, terms, and conditions when load and generation sit on the same side of an interconnection point.
  • Paired studies for "electrically proximate" load, meaning load within two substations of a generator, completed in roughly 60 to 90 days, to avoid unnecessary new transmission.
  • Financial deposits and milestones to discourage speculative or duplicate requests from utilities shopping the same customer to several sites.
  • Grid-enhancing technologies such as dynamic line ratings to free up capacity on existing lines.

Operators also had 30 days to file reports explaining how they will ensure enough generation to serve both existing customers and new large loads. That question sits at the center of PJM's capacity shortfall.

Where it stands now

The 60-day response deadline fell on August 17, 2026. The operators are on different tracks, and several asked FERC to hold their dockets in abeyance, meaning paused, while regional stakeholder processes finish their own proposals. PJM's response is centered on a fast-tracked stakeholder process for a reliability backstop procurement mechanism and rules for serving load when resources are insufficient. FERC separately accepted PJM's Expedited Interconnection Track for generation in June. MISO previewed a zero-injection generator interconnection agreement and a parallel study process for large loads.

The upshot is that binding tariff rules will arrive region by region over late 2026 and into 2027, not all at once. The six proceedings are FERC Dockets EL26-67 through EL26-72.

Why this matters if you are not a data center

Your capacity and transmission costs. Large-load growth is the main force behind PJM's capacity auctions clearing at the price cap. Rules that connect load faster without matching new supply keep that pressure on. Rules that tie new load to new generation, or reward flexibility, relieve it. How upgrade costs are allocated between new large loads and existing customers will also shape future transmission charges.

You may be a large load yourself. A new or expanding manufacturing plant, cold storage campus, or electrified industrial process can cross a 50 MW threshold. If you are planning a load addition of that size, these rules will govern your timeline and deposit requirements.

Flexibility is becoming currency. A recurring theme across the proceedings is faster treatment for loads that agree to curtail during grid stress. PJM is developing a participation model for price-responsive large loads. For facilities that can shift or shed load, experience with demand response is becoming an interconnection asset as well as a savings strategy.

Siting decisions. Where load can connect quickly will increasingly shape where it locates. That in turn affects local congestion and basis for everyone nearby.

What to watch

Watch FERC's orders on each operator's response and any abeyance requests. Watch PJM's reliability backstop filings and how their costs are allocated. And watch whether FERC extends similar expectations to utilities outside RTO regions, which it has encouraged to file their own large-load rules. The companion pieces on the interconnection queue and resource adequacy cover the supply side of the same problem.

Common questions

What did FERC order on large load interconnection?
On June 18, 2026, FERC issued show cause orders under Section 206 of the Federal Power Act to PJM, MISO, SPP, CAISO, ISO-NE, and NYISO. The orders preliminarily found each tariff unjust and unreasonable for lacking clear rules on connecting large loads and co-located load, and required each operator to justify its rules or propose revisions within 60 days.
What counts as a large load?
In the June 2026 orders, FERC suggested defining a large load as a new facility over 50 MW that takes transmission service above 69 kV and is not part of a co-located arrangement. Definitions may differ by region as each grid operator finalizes its tariff rules.
What is co-located load?
Co-located load is a large electricity user, often a data center, that is physically connected to a generating plant on the same side of the grid interconnection point. FERC has required grid operators to set clear rates, terms, and conditions for these arrangements so that co-located loads pay appropriately for the grid services they use.
How do FERC's large load rules affect commercial electricity costs?
Large-load growth drives capacity prices and transmission investment. The rules determine how quickly new load connects, whether it must bring or be paired with new supply, and how grid upgrade costs are allocated between new large loads and existing customers. Those outcomes flow through to capacity and transmission charges on commercial bills.
When will the new large load rules take effect?
Grid operators' responses were due August 17, 2026, and several asked FERC to pause their dockets while regional stakeholder processes finish. Final tariff rules are expected to arrive region by region from late 2026 into 2027. The proceedings are FERC Dockets EL26-67 through EL26-72.