Pilot Energy 05/26/2026 Policy
7 min read

On a napkin

PJM Capacity Auction Clearing Price ($/MW-day) $400 $200 $50 $0 23/24 $34 24/25 $28.92 25/26 $269.92 ~10× 26/27 $329.17 capped 27/28 $333.44 capped Drivers Data centers ↑↑↑ Electrification ↑ Retirements ↑ ELCC change Queue backlog PJM peak load forecast +5,400 MW yr/yr — largely data centers

The short version

Data center electricity demand — driven by cloud computing growth and accelerated by AI training and inference — is the dominant new load story in US electricity markets. After two decades of flat or declining US electricity demand, data centers (combined with electrification of transportation and buildings) are driving the first sustained load growth period since the late 1990s. The effects: capacity prices at record highs, transmission planning struggling to keep pace, hyperscaler procurement strategies pulling unconventional resources online, and a regulatory scramble across every major ISO to figure out who pays for what.

PJM capacity prices tell the story. The 2024/25 BRA cleared at $28.92/MW-day. The 2025/26 BRA cleared at $269.92 — a nearly 10× increase. The 2026/27 and 2027/28 BRAs both cleared at the FERC-approved price cap ($329.17 and $333.44 respectively). The 2027/28 auction was the first in PJM history where the entire RTO fell short of the reliability requirement. PJM's forecast peak load is growing by over 5,400 MW per delivery year — most of it data centers.

The scale of the demand growth

US data centers consumed approximately 4.4% of total US electricity in 2023, projected to grow to 6-12% by 2028 depending on AI adoption pace. The magnitude of individual data center loads has shifted dramatically: traditional cloud data centers drew 20-50 MW; hyperscale AI training campuses now draw 100-500 MW continuously. Reports of single proposed sites reaching 1,000-2,000 MW (1-2 GW) are increasingly common — each equivalent to multiple large nuclear units.

Major data center hubs include Northern Virginia's Loudoun County (the world's largest, over 4 GW operational), Phoenix-Mesa AZ, Dallas-Fort Worth TX, Columbus OH, Atlanta GA, Chicago IL, Quincy WA, and Reno NV. Newer development is shifting toward areas with available power capacity — the Texas Panhandle, the Mississippi Delta, Wyoming, and other regions with available transmission capacity and faster permitting. ERCOT large load interconnection requests quadrupled in 2025, with utilities and ERCOT itself proposing new approval frameworks to manage demand requests well in excess of available supply.

How capacity prices reflect the shock

PJM's capacity market is the most affected. The 2025/26 BRA cleared at $269.92/MW-day RTO-wide ($466.35 in BGE, $444.26 in Dominion) — a 10× increase driven primarily by data center load growth combined with generator retirements and a methodological change to marginal ELCC accreditation. The 2026/27 BRA cleared at $329.17/MW-day at the FERC-approved price cap, with all four major LDAs constrained. The 2027/28 BRA cleared at $333.44 (also capped) and was the first auction where the entire RTO fell short of its reliability requirement.

For commercial customers in PJM, this translates directly to higher capacity costs. A 10 MW industrial facility's annual capacity cost rose from roughly $105,000 at the 2024/25 price to over $1.2 million at the 2027/28 price — a roughly $1.1 million increase. Customers with high coincident peak (CP) tags face the largest exposures, making CP management more economically critical than ever.

The hyperscaler procurement playbook

Major data center operators have responded with aggressive procurement strategies that increasingly bypass conventional utility supply. Microsoft signed a 20-year PPA with Constellation Energy to restart Three Mile Island Unit 1 (the undamaged reactor). Amazon's AWS bought a data center campus co-located with Talen Energy's Susquehanna nuclear plant. Google, Meta, and other hyperscalers have signed massive solar, wind, and storage PPAs — collectively the largest corporate procurement portfolios ever assembled.

New approaches include nuclear co-location (data centers physically adjacent to nuclear plants, drawing dedicated output), behind-the-meter gas turbines (operators building their own generation on-site), and large-scale battery storage (providing backup and grid services). The regulatory and reliability implications are significant: co-located generation that doesn't deliver to the grid raises questions about cost allocation, stranded grid investment, and reliability contributions. FERC, PJM, and state regulators are actively developing new frameworks for how these arrangements should be treated.

What this means for everyone else

For commercial and industrial customers without unique data center load characteristics, the AI data center surge means significantly higher capacity costs, accelerated transmission rate cases, and intensifying competition for available generation capacity. PJM's market monitor and others have raised concerns about data center load growth crowding out other customers' supply or imposing reliability risks. Several regulatory reforms are in process — large load interconnection rules, demonstrations of supply availability, and special tariff structures — but the underlying tension between demand growth and supply additions is unlikely to resolve quickly. For procurement teams, this argues for locking in longer-term contracts, prioritizing CP/peak management, and pursuing on-site generation where feasible to reduce exposure to capacity price escalation.

Common questions

How much electricity do data centers consume?
US data centers consumed approximately 4.4% of total US electricity in 2023, projected to grow to 6-12% by 2028 depending on AI adoption pace. A single hyperscale AI data center may draw 100-500 MW continuously — equivalent to a small city. AI training and inference workloads consume substantially more power per server than traditional cloud computing, accelerating the load growth curve significantly above pre-AI projections.
How are data centers affecting capacity prices?
Rapid data center load growth is a primary driver of capacity price increases in PJM and other ISOs. PJM's 2025/26 BRA cleared at $269.92/MW-day (up from $28.92 in the prior auction), and the 2026/27 and 2027/28 auctions cleared at the FERC-approved cap of $329.17/MW-day and $333.44/MW-day respectively. Data center load growth — combined with generator retirements and electrification — has tightened the supply-demand balance across multiple ISOs, with PJM forecasting peak load growth of 5,400+ MW per delivery year.
Where are data centers concentrating?
Major US data center hubs include Northern Virginia (Loudoun County, the world's largest), Phoenix and Mesa AZ, Dallas-Fort Worth TX, Columbus OH, Atlanta GA, Chicago IL, Quincy WA, and Reno NV. Newer development is shifting toward areas with available power capacity. Northern Virginia's Loudoun County alone has over 4 GW of operational data center capacity with multiple GW more under development.
How are utilities responding to data center demand?
Utility responses vary. Some utilities are accelerating new generation procurement and transmission upgrades. Dominion Energy in Virginia has signed power purchase agreements for new gas, nuclear (small modular reactors), and renewable generation. ERCOT large load requests in Texas quadrupled in 2025. Several utilities have proposed special tariffs for large new loads (often called large load tariffs or LLTs) requiring co-investment in transmission upgrades. PJM filed proposed reforms to require demonstration of supply availability before approving large loads.
Are data centers using behind-the-meter generation?
Yes, increasingly. Many hyperscale operators have signed power purchase agreements for dedicated nuclear (including AWS at Talen's Susquehanna and Microsoft's Three Mile Island restart with Constellation), large-scale solar, and gas turbines. Some operators are pursuing co-located generation to avoid grid interconnection delays — buying or building generation on the same site as the data center. This approach is faster to deploy than grid-served alternatives but raises regulatory questions about cost allocation.

Want to put this knowledge to work?

Learn about Energy Procurement Talk to an Advisor

Need help navigating this topic?

Pilot Energy’s advocacy team can help you make sense of the energy landscape and build a strategy that works for your organization.

Talk to an Advisor

Tag:

Policy



Related Articles

It is a long established fact that a reader will be distracted by the readable content of a page when looking at its layout.

The Inflation Reduction Act + OBBBA

On a napkin The IRA → OBBBA transition · what survived, what didn't, what got extended Terminated / sunset accelerated phaseout Wind & solar generation 45Y PTC · 48E ITC PIS after Dec 31, 2027 12-mo BOC safe harbor Consumer EV (30D) ended Sept 30, 2025 Commercial EV (45W)

State renewable portfolio standards

On a napkin Major State RPS Targets & Years 100% 50% 0% HI 100% by 2045 CA 100% clean by 2045 NY 100% zero by 2040 NJ 50% by 2030 CT 48% by 2030 MA 35% by 2030 +1pp/yr IL 50% by 2040 PA 8% Tier I (2021) TX 5,880

New York's CLCPA

On a napkin CLCPA Targets & Implementation Status (May 2026) 2030 70% renewable electricity Status: off track — likely ~2033 2030 40% GHG reduction (vs. 1990) Status: off track — only ~10% reduction by 2021 2035 9 GW offshore wind Status: significantly behind —

Pilot Energy Background

Ready to take control of your energy strategy?

Pilot Energy has spent 25 years helping commercial and industrial organizations navigate complex energy markets. Let our advocacy team put that experience to work for you.