Pilot Energy 05/26/2026 Grid Ops
8 min read

On a napkin

Four approaches to ensuring enough generation Centralized capacity mkts PJM · ISO-NE · NYISO · MISO Annual auction sets price Generators paid to be available Load required to procure PJM 2027/28: $333/MW-day Bilateral RA CAISO LSEs contract bilaterally Annual + monthly showings CPUC sets RA requirements Slice-of-day shaping Energy-only + scarcity ERCOT No capacity payments $5,000/MWh price cap ORDC scarcity adders DRRS being added 2025+ What capacity costs add to a typical C&I bill PJM $25–40/MWh ISO-NE $15–25/MWh NYISO $10–18/MWh MISO $8–15/MWh CAISO $5–15/MWh* ERCOT $0** *bilateral **embedded in energy price

The short version

Every grid operator faces the same physical reality: enough generation must be available to meet the next peak demand event with high probability. They use radically different mechanisms to ensure this happens. The Eastern ISOs — PJM, ISO-NE, NYISO, MISO — operate centralized capacity markets that auction off the right to be paid for being available. CAISO uses a bilateral resource adequacy (RA) program where load-serving entities contract directly with generators to meet capacity requirements set by the California Public Utilities Commission. ERCOT alone uses an energy-only design with no capacity payments, relying on scarcity pricing to provide investment signals. Each approach has different costs, different risks, and different implications for commercial procurement.

The cost difference is meaningful. Capacity charges add roughly $25-40/MWh to PJM bills today (after 2024-2025 auctions hit the FERC price cap), $15-25/MWh in ISO-NE, $10-18/MWh in NYISO, and $8-15/MWh in MISO. CAISO RA costs vary by LSE and contract but typically add $5-15/MWh. ERCOT has zero explicit capacity charge — though scarcity pricing during reliability events can drive average energy prices substantially higher than other regions over time. The total all-in cost of capacity ends up surprisingly similar across regions; what differs is how it's allocated, hedged, and exposed to volatility.

Capacity markets (PJM, ISO-NE, NYISO, MISO)

Centralized capacity markets work the same way structurally. The ISO calculates the total capacity requirement for an upcoming delivery year based on forecasted peak load plus a planning reserve margin (typically 12-18% above peak). Generators submit offers indicating the price at which they're willing to commit capacity. The ISO clears the auction at the price needed to procure the required quantity — all cleared generators receive the clearing price for every MW for the entire delivery year. The clearing price is then collected from load-serving entities proportional to their forecasted load contribution at peak, who pass costs through to retail customers.

PJM runs the Base Residual Auction (BRA) three years ahead of the delivery year. The 2026/27 BRA cleared at $329.17/MW-day across the entire footprint, hitting the FERC-imposed price cap. The 2027/28 BRA, cleared December 2025, repeated this outcome at $333.44/MW-day — the first time the entire RTO hit the cap, indicating severe capacity shortage. Drivers include rapid data center load growth, electrification, generator retirements, and slow new build progressing through the interconnection queue. ISO-NE's Forward Capacity Market runs three years ahead with reconfiguration auctions closer to delivery. NYISO uses a strip auction model with monthly spot auctions. MISO implemented a seasonal capacity construct starting in 2022 to address reliability events.

CAISO's bilateral RA

CAISO does not operate a centralized capacity market. Instead, California uses a bilateral resource adequacy program where each load-serving entity is required by the California Public Utilities Commission to contract with sufficient generation to meet RA requirements. LSEs must demonstrate compliance through annual and monthly RA showings — providing evidence that they have contracted for enough accredited capacity to cover their share of system needs.

The CAISO RA framework evolved significantly with the implementation of slice-of-day shaping starting in 2025. Rather than just meeting a peak hour requirement, LSEs must now demonstrate capacity availability across all 24 hours, with particular focus on the late afternoon/early evening ramp when solar production declines but load remains high. This change addresses the resource adequacy gap that contributed to the August 2020 rotating outages and reflects the increasing importance of energy availability over multiple hours rather than just instantaneous peak coverage.

ERCOT's energy-only design

ERCOT operates an energy-only market without capacity payments — the only major US ISO to do so. The theory: when generation is tight, wholesale energy prices should rise to scarcity levels that provide adequate revenue signals for generators to maintain availability and for investors to build new capacity. ERCOT implements this through the Operating Reserve Demand Curve (ORDC), an administrative scarcity pricing adder that increases LMPs above marginal cost when operating reserves fall below specified thresholds. The wholesale price cap was reduced from $9,000/MWh to $5,000/MWh in 2023.

Winter Storm Uri (February 2021) exposed weaknesses in the energy-only design. The Performance Credit Mechanism (PCM) was proposed as a hybrid that would add partial capacity payments without creating a full capacity market — but was shelved by the Public Utility Commission of Texas in December 2024 after years of debate. ERCOT is instead implementing the Dispatchable Reliability Reserve Service (DRRS), real-time co-optimization of energy and ancillary services, and ORDC reforms. The bet is that targeted reliability services within an energy-only framework can deliver adequate reliability without the structural cost overhead of a capacity market — though the bet is being stress-tested as ERCOT's load grows four times faster than expected.

ELCC and the accreditation problem

The conceptual challenge with capacity markets is how to credit variable resources — wind, solar, and storage — that don't behave like dispatchable thermal generators. ISOs increasingly use Effective Load Carrying Capability (ELCC) methods that measure the marginal contribution of a resource to system reliability rather than crediting nameplate capacity. A solar facility with 100 MW nameplate might receive only 20-30 MW of ELCC accreditation; a battery's ELCC depends on duration (a 100 MW / 4-hour battery might receive 80+ MW ELCC, but only if other batteries aren't already saturating the system).

ELCC accreditation has reduced capacity contributions of intermittent resources, contributing to the capacity price increases observed in 2024-2025. This is mathematically inevitable: when wind and solar with nameplate capacity displace fully-credited thermal generation, total accredited capacity declines even as installed nameplate grows. The result is higher capacity prices to procure enough accredited capacity, channeling revenue back to remaining dispatchable resources (gas plants, demand response, storage) while creating ongoing pressure to procure more storage and demand response to fill the gap. For commercial buyers, the implication is that capacity charges will likely remain elevated in capacity-market regions through the late 2020s and beyond.

Common questions

What is resource adequacy?
Resource adequacy is the framework grid operators use to ensure enough generation capacity is available to meet expected peak demand with acceptable reliability — typically targeting a loss-of-load expectation of one event in ten years. PJM, ISO-NE, NYISO, and MISO operate centralized capacity markets. CAISO uses a bilateral RA program. ERCOT relies on energy-only scarcity pricing without capacity payments.
How do capacity markets work?
Capacity markets are auctions where generators bid the amount of capacity they will guarantee to deliver during peak periods. The ISO sets the demand requirement based on forecasted peak load plus a reliability margin, and the auction clears at the price needed to procure that quantity. Cleared capacity earns the clearing price for every MW for the delivery year. Recent PJM auctions cleared at $329.17/MW-day (2026/27) and $333.44/MW-day (2027/28), both hitting the FERC-imposed price cap.
What is ELCC accreditation?
Effective Load Carrying Capability is the method ISOs use to assign accredited capacity values to variable resources like wind, solar, and storage. Rather than crediting at full nameplate, ELCC measures the additional load the system can serve reliably by adding that resource. ELCC accreditation has reduced capacity contributions of intermittent resources, contributing to capacity price increases.
What is the LOLE standard?
Loss of Load Expectation is the reliability standard most US planning regions use — typically expressed as one day of insufficient generation in ten years (0.1 days/year). The reserve margin required to meet 1-in-10 LOLE typically ranges from 12% to 18% of expected peak demand, varying by region.
Why has ERCOT chosen not to have a capacity market?
ERCOT relies on energy-only scarcity pricing — when supply is tight, wholesale prices rise toward the $5,000/MWh cap through the ORDC. The Performance Credit Mechanism that would have added partial capacity payments was shelved by the Texas PUC in December 2024. ERCOT continues to refine its energy-only design through DRRS, real-time co-optimization, and ORDC reforms.

Want to put this knowledge to work?

Learn about Energy Procurement Talk to an Advisor

Need help navigating this topic?

Pilot Energy’s advocacy team can help you make sense of the energy landscape and build a strategy that works for your organization.

Talk to an Advisor

Tag:

Grid Ops



Related Articles

It is a long established fact that a reader will be distracted by the readable content of a page when looking at its layout.

Transmission & congestion

On a napkin Cheap gen here, expensive load there, wire in between is full Generation node Wind / solar farms Western PJM $22/MWh marginal cost CONSTRAINED at thermal limit Load zone Data centers N. Virginia (DOM) $78/MWh local marginal gas unit

Weather & grid risk

On a napkin Four weather threat patterns + grid stress modes Extreme cold Winter Storm Uri · Feb 2021 • Heating load surge • Gas-electric coupling: gen fuel cut • Wind turbines ice up • Coal piles freeze, instruments fail Result: 30+ GW out · 246 deaths TX Extreme heat

Black start & resilience

On a napkin Building the grid back up from zero 1. Self-start unit Hydro / battery+GFM on-site fuel Starts itself. Energizes line. 2. Cranking path Transmission line energized to neighbor Carries power to wake up next generator 3. Wake larger gen Gas /