On a napkin
Data as of September 30, 2026. Figures are PJM RTO clearing prices; sources linked inline.
The short version
The capacity charge on a PJM commercial bill is set by two things decided long before the invoice arrives: a price, fixed at an auction held one to three years earlier, and your share of the obligation, fixed by your load during the grid's five highest summer peak hours the year before. Multiply your peak load contribution (PLC, or capacity tag) by the zonal capacity price and the number of days in the period, adjust for PJM's scaling factors, and you have your capacity cost.
That lag is why 2026 bills look the way they do. The capacity auction for the delivery year that started June 1, 2026 cleared at $329.17/MW-day across the RTO, the price cap. The auction before it cleared at $269.92, and the one before that at just $28.92. Buyers whose contracts renewed across that jump saw capacity go from a rounding error to one of the largest lines on the bill.
Rule of thumb: multiply the $/MW-day price by 365 to get an annual cost per MW of capacity tag. At $329.17, a 1 MW tag costs roughly $120,000 a year before scaling factors.
From auction to invoice: the timeline
PJM's capacity market procures supply through the Base Residual Auction (BRA). Each auction covers one delivery year running June 1 through May 31. After the 2025/26 auction, PJM compressed its schedule to catch up, so several auctions were held less than the usual three years ahead. Here is how recent results map to bill periods:
- 2024/25 (June 2024–May 2025): $28.92/MW-day. The last low-price year.
- 2025/26 (June 2025–May 2026): $269.92/MW-day, auction held July 2024. BGE and Dominion zones cleared higher, at $466.35 and $444.26.
- 2026/27 (June 2026–May 2027): $329.17/MW-day, auction held July 2025. The first auction under the FERC-approved price collar, and the year on bills now.
- 2027/28 (June 2027–May 2028): $333.44/MW-day, auction held December 2025. The first time the entire RTO fell short of its reliability requirement.
- 2028/29 (June 2028–May 2029): $325.00/MW-day, auction held July 2026. A third straight auction at the cap, with committed supply 6,831 MW short of the reliability requirement.
Sources: PJM's 2027/2028 BRA report (historical clearing prices) and 2028/2029 BRA results.
How your capacity tag gets set
In most of PJM, your tag is based on the five coincident peaks (5CP): the five highest system-load hours, on five different weekdays, between June 1 and September 30. After the summer ends, your utility looks at your metered load during each of those hours, averages them, and scales the result so that all customers' tags add up to the zone's weather-normalized peak. That value becomes your PLC for the delivery year that begins the following June.
The practical consequence: the peaks that occurred this past summer set your tag for June 2027 through May 2028, the delivery year priced at $333.44. Load you avoided during those hours has already locked in savings for that year. Load you didn't avoid is locked in too. The mechanics, and how to run a peak-response program, are covered in coincident peak management.
Utilities apply these rules under state-approved methodologies, and details vary. Customers without interval meters get a tag estimated from their rate class profile. Your tag is usually printed on your bill or available from your supplier. Transmission charges use a separate value, the network service peak load (NSPL), typically based on your zone's single highest peak hour.
What the math looks like for a real facility
Take a manufacturer with a 2 MW capacity tag and hold that tag constant. Using nominal RTO prices (price × 365 × 2 MW), its annual capacity cost moves like this:
- 2024/25: about $21,100
- 2025/26: about $197,000
- 2026/27: about $240,300
- 2027/28: about $243,400
- 2028/29: about $237,300
Actual invoiced amounts also reflect PJM's forecast pool requirement and zonal scaling factors, which typically push the effective charge somewhat above the nominal figure, and zones that clear above the RTO price (as BGE and Dominion did in 2025/26) pay more. The direction is the point: the same facility, with the same load, now carries more than ten times the capacity cost it did two years ago. Every megawatt shaved from the tag is worth roughly $119,000 to $122,000 a year at current prices.
Where your contract decides who pays
Whether that increase lands on you, and when, depends on your retail electricity contract. In a fixed all-in contract, the supplier priced capacity into your rate when you signed. If you locked in before the July 2024 auction for delivery periods after it, your supplier absorbed the increase for the remaining term. In a capacity pass-through contract, you pay the actual capacity charge as it changes, so the increase showed up immediately.
Two clauses deserve a close read at renewal. The first is how capacity is defined and billed, including whether the tag used is fixed at signing or updated each June. The second is change-in-law or regulatory-event language, which some suppliers use to pass through costs from market rule changes such as a new price collar or backstop procurement. The trade-offs between locking and floating are covered in fixed vs. index pricing.
What happens next
The price collar that has held auctions at the cap has been extended through the 2029/2030 auction. Without it, PJM's own simulation found the 2028/29 auction would have cleared at $554.72/MW-day RTO-wide and $776.69 in the ComEd zone, per an analysis of the auction results. In other words, the cap is holding prices down, and supply remains short. PJM has also moved toward a reliability backstop procurement to address the shortfall, whose costs could flow to load.
For budgeting, the reasonable planning assumption is that capacity stays near current levels through at least the 2029/30 delivery year. The drivers are covered in data center load growth and resource adequacy frameworks.
What to do with this
Start by finding your current PLC and your contract's capacity treatment, then build a multi-year budget using the delivery-year prices above. If your facility can curtail or shift load for a few hours on hot summer afternoons, a peak-response program or demand response enrollment is likely the highest-return action available. Behind-the-meter storage can make that response automatic. If a renewal is coming up, compare fixed and pass-through offers against the known prices for the delivery years your term will cover.
Common questions