The OBBBA deadlines and PPA pricing

The OBBBA's July 4, 2026 begin-construction deadline and December 31, 2027 in-service deadline for wind and solar, FEOC material assistance thresholds, storage credit phase-down, and what they mean for PPA prices.

⏱ 9 min read · Policy

On a napkin

Federal clean electricity credit eligibility after the OBBBA Decision tree. Wind and solar projects that began construction by July 4, 2026 generally keep four years to be placed in service; those that did not must be placed in service by December 31, 2027 or lose the 45Y and 48E credits. Storage and other technology-neutral projects keep full credits for construction starting through 2033, then 75 percent in 2034, 50 percent in 2035 and none from 2036. Any project starting construction after December 31, 2025 must also pass the FEOC material assistance test: at least 40 percent non-prohibited-foreign-entity content for generation and 55 percent for storage in 2026, rising each year. New clean power project Wind or solar Began construction by July 4, 2026? yes no Generally keeps 4 years to reach service (continuity) Must be in service by Dec 31, 2027, or no 45Y/48E credit Storage, other tech Full credit if construction begins through 2033 Phase-down by construction start: 2034: 75% · 2035: 50% 2036 onward: none Every path: construction starting after Dec 31, 2025 must pass the FEOC material-assistance test 2026 minimum non-PFE cost share: 40% for generation, 55% for storage. Thresholds rise each year.

Data as of September 30, 2026. This is educational information, not tax or legal advice; sources linked inline.

The short version

The One Big Beautiful Bill Act (OBBBA), signed July 4, 2025, put a clock on federal credits for new wind and solar. That clock's first deadline has now passed. Wind and solar projects that began construction by July 4, 2026 keep access to the clean electricity production and investment credits (45Y and 48E) and generally have four years to be placed in service. Projects that missed that date must be placed in service by December 31, 2027, or they get no credit at all.

Battery storage and other technology-neutral resources were treated far more gently: full credits for projects starting construction through 2033, then a phase-down. Layered on top of everything is a new set of foreign-sourcing restrictions, the FEOC rules, which apply to projects that began construction after December 31, 2025.

For corporate buyers, this splits the renewable pipeline into distinct cohorts with different prices, different risks, and different contract terms. The broader credit landscape is covered in the Inflation Reduction Act + OBBBA. This page focuses on what the deadlines mean for anyone signing a power purchase agreement.

What counted as "beginning construction"

The date a project began construction is a tax concept, not the day a shovel hits dirt, and the rules for it tightened. Under longstanding IRS guidance, developers could establish a start date either by starting physical work of a significant nature or by incurring at least 5% of total project cost. In August 2025, Treasury's Notice 2025-42 eliminated that 5% safe harbor for wind and solar, except for small solar facilities of 1.5 MW or less. That leaves most projects relying on the physical work test, plus a requirement to maintain continuous construction afterward.

The tightened rules apply to projects that began construction on or after September 2, 2025. Projects that started earlier can rely on the prior, more flexible guidance. For a buyer evaluating a project, the question is not whether the developer says it is "safe harbored," but which test it relied on and what documentation supports it.

Key distinction: For wind and solar, the July 4, 2026 date is about when construction began. December 31, 2027 is about when the project is placed in service. A project that missed the first deadline must hit the second, about fifteen months after this page's September 2026 update.

The FEOC rules: a second eligibility test

Separately, the OBBBA bars "prohibited foreign entities" (PFEs) from claiming credits and limits how much project equipment can come from them. The equipment limit is measured with a material assistance cost ratio (MACR): the share of a facility's direct costs that does not come from a PFE. For construction starting in 2026, that share must be at least 40% for generating facilities and at least 55% for storage, and the thresholds rise each year.

Treasury and the IRS issued interim guidance on the calculation in February 2026 (Notice 2026-15), letting taxpayers use existing domestic-content cost tables as safe harbors. Formal proposed regulations and new safe harbor tables are still to come, and the law requires the tables by December 31, 2026. Until they arrive, FEOC compliance is an area where buyers should expect representations, warranties, and indemnities in contracts.

Three cohorts in today's renewable pipeline

Safe-harbored projects. These are wind and solar projects that credibly began construction before the deadline, and ideally before 2026, which also keeps them outside the FEOC material assistance test. They carry full credit value and a comfortable service window, so they are the most valuable projects to buyers and are priced accordingly. Supply is finite: no new wind or solar project can join this group.

Race-to-2027 projects. These projects missed the construction deadline but are far enough along to be in service by the end of 2027. Their credit value depends entirely on the schedule, so interconnection delays, equipment delivery, and permitting become tax risks as well as operational ones.

Post-credit projects. New wind and solar developed without federal credits must recover their full cost through the contract price. Expect higher prices, and a larger role for storage, which keeps its credits, and for hybrid structures that pair the two.

What PPA prices are doing

Prices were climbing before the deadline arrived. LevelTen Energy reported that North American PPA prices in Q1 2026 reached their highest level since its index began in 2018. In Q2 2026, market-averaged solar prices fell 4.8% quarter over quarter, the first decline in two years, largely driven by California. Wind rose another 5.5% and is up 17.5% year over year, amid a shortage of fully permitted wind projects. Continental averages for the quarter were about $61/MWh for solar, $84/MWh for wind, and $73/MWh for blended portfolios.

Read those figures as offers on projects that were, in most cases, positioned to capture credits. As the safe-harbored pipeline is contracted, the marginal project a buyer can sign moves toward the race-to-2027 and post-credit cohorts, with price and risk moving with it.

Contract terms that now matter more

Credit status has moved from a developer's problem to a term sheet issue. When evaluating a physical PPA or a virtual PPA, look closely at:

  • Credit qualification representations: which beginning-of-construction test the project relied on, and what happens if a credit is later disallowed.
  • Commercial operation date protections: delay damages, termination rights, and whether a missed 2027 in-service date reprices the contract.
  • Change-in-tax-law and price adjustment clauses: many developers now include mechanisms that let price move with tariffs, credit outcomes, or FEOC determinations.
  • FEOC compliance covenants: who bears the cost if sourcing fails the material assistance test.

A lower headline price with weak protections can cost more than a higher price with firm ones. Buyers who also purchase transferable credits face the same diligence questions from the other side.

Related deadlines that already passed

The OBBBA also ended credits outside the power sector. The 30C credit for EV charging infrastructure and the 179D deduction for energy-efficient commercial buildings were set to expire June 30, 2026. See commercial EV charging and building electrification for how that changes project economics.

Common questions

What is the OBBBA deadline for wind and solar tax credits?
Under the One Big Beautiful Bill Act, wind and solar projects that began construction by July 4, 2026 generally keep eligibility for the 45Y and 48E credits if they are placed in service within four years. Projects that began construction after that date must be placed in service by December 31, 2027 to qualify.
Does the OBBBA end tax credits for battery storage?
No. Battery storage and other technology-neutral resources keep full credit value for projects that begin construction through 2033. The credit then drops to 75% for construction starting in 2034, 50% in 2035, and ends for projects starting in 2036 or later. Storage projects must still meet the FEOC material assistance requirements.
What are the FEOC rules for clean energy projects?
The foreign entity of concern (FEOC) rules bar prohibited foreign entities from claiming clean energy credits and limit how much equipment can come from them. For projects beginning construction in 2026, at least 40% of a generating facility's direct costs, or 55% for storage, must come from non-prohibited sources. The thresholds rise each year, and Treasury must publish safe harbor tables by December 31, 2026.
What does "beginning of construction" mean for tax credits?
It is the tax-law date a project is treated as starting. Notice 2025-42 eliminated the 5% cost safe harbor for most wind and solar projects starting on or after September 2, 2025, leaving the physical work test: starting physical work of a significant nature and then maintaining continuous construction. Solar facilities of 1.5 MW or less can still use the 5% safe harbor.
How will the OBBBA affect PPA prices?
Projects that secured credit eligibility are finite and command a premium, while projects without credits must recover their full cost through the contract price. PPA prices hit record highs in early 2026. In Q2 2026, North American solar averaged about $61/MWh and wind about $84/MWh on LevelTen's index, with wind still rising. Buyers should expect upward pressure as the credit-eligible pipeline is contracted.